Analisis Perbandingan Aplikasi Program Microsoft Project Dan Metode Cpm Dalam Penjadawalan Proyek Konstruksi
This work is licensed under a Creative Commons Attribution 4.0 International License.
- Articles
- Issue: Vol. 9 No. 1 (2024)
-
Published: May 13, 2024
Abstract
This research is a descriptive analysis, namely describing the condition of the construction of the Ganesha Hotel by collecting data from the project using this method to analyze the efficiency, time and cost of research using the Ms Project application and the Critical Path Method. The prediction results for each segment are compared to make a comparison to find out which work needs to be done. comes first and work that doesn't need to come first. From the research carried out, it can be concluded that in the research process using Ms Project, the results were that the completion time was 189 days from the project plan of 210 days, so there was a time efficiency of 21 days, whereas in the research using CPM, the results were that the completion time was 188 days from the project plan of 210 days, so there were efficiency 22 days From the research we conducted to compare the time of Ms Project and Critical Path Method there is a difference of one day while for the costs obtained from comparing the 2 methods IDR 26,426,500,000
Downloads
ANDHIKA, M. JURNAL TUGAS AKHIR PERENCANAAN PENJADWALAN PROYEK.
Dahlan, A., Nainggolan, T. H., & Ratnawinanda, L. A. (2019). Evaluasi Pengendalian Waktu Dan Biaya Menggunakan Metode Critical Path Method (CPM) Dan Fast Track. Student Journal GELAGAR, 1(1), 24-31.
Ervianto, W. I. (2023). Manajemen proyek konstruksi. Penerbit Andi
Husen, A. (1994). Perencanaan Penjadwalan & Pengendalian Proyek. Yogyakarta: CV Andi Offset. Sastraatmadja, Soedrajat.
Mertha Jaya, N., & Diah Parami Dewi, A. A. (2007). Analisa Penjadwalan Proyek Menggunakan Rangked Positional Weight Method (Studi Kasus: Proyek Pembangunan Pasar Mumbul di Kabupaten Buleleng). Jurnal Ilmiah Teknik Sipil, 11(2), 100-108.
Utomo, G., Hendriyani, I., & Aida, S. N. (2020). Evaluasi Pelaksanaan Proyek Drainase Dengan Metode CPM Dan PERT: Drainage Project Implementation Evaluation With The CPM And PERT Method. Media Ilmiah Teknik Sipil, 9(1), 44-52.
Yusdiana, E. D., & Satyawisudarini, I. (2018). Penerapan metode pert dan cpm dalam pelaksanaan proyek pembangunan jalan paving untuk mencapai efektivitas waktu penyelesaian proyek. Almana: Jurnal Manajemen dan Bisnis, 2(3), 20-30.
Title | Analisis Perbandingan Aplikasi Program Microsoft Project Dan Metode Cpm Dalam Penjadawalan Proyek Konstruksi |
---|---|
Issue: | Vol. 9 No. 1 (2024): JURNAL PILAR TEKNOLOGI |
Section | Articles |
Published: | May 13, 2024 |
DOI: | https://doi.org/10.33319/piltek.v9i1.171 |
Keywords: | Microsoft Project, Critical Path Method (CPM), Manajemen proyek |
Author | Faathir thaariq faathir |